Hi everyone,
I am making this post as a warning to anyone in Bengaluru currently considering HUB Interiors for their home. I am a highly compliant client who cleared 90% of my total project costs strictly on time through their system triggers, yet my family is currently facing physical displacement due to their utter lack of accountability, broken leadership commitments, and operational negligence.
They are actively trying to twist the facts on Google Reviews using public relations damage control, so I am putting the entire documented timeline out here with complete proof.
The Fact-Checked Timeline vs. HUB's Blatant Lies:
April 23, 2026 – Design Sign-Off: I gave final email approval on all drawings. My project was moved to production.
April 28, 2026 – Official Commitment: HUB’s Production Manager issued an official schedule explicitly guaranteeing a Baseline Handover by June 17, 2026, and an absolute maximum Extended Handover by June 25, 2026.
May 15, 2026 – HUB Flags Internal Delay: HUB sent me an official email admitting to a "production and procurement delay" due to their own supply chain vulnerabilities. Note this date carefully: This was 6 days BEFORE they even received my apartment keys.
May 21, 2026 – Key Handover: Keys were officially handed over to their team.
June 2, 2026 – Ground Neglect Escalation: After zero execution updates, I filed a formal escalation. A basic 144.5 sq. ft. local false ceiling has been sitting half-finished on my site for weeks. Local vendors confirm it is a 3-day job max, but HUB completely abandoned it. (Images attached)
June 8, 2026 – Broken Leadership Promise: On a virtual escalation call, Senior Manager Balaji explicitly promised to share a comprehensive, day-by-day ground execution schedule over that immediate weekend. They completely ghosted that commitment.
June 18, 2026 (Today) – Automated Scripts & Review Suppression: Their Care team responded to my escalation email by completely dodging my request for an in-person meeting, telling me to wait another week for a random factory update. Worse, they called me yesterday asking me to take down my negative Google Review instead of providing the schedule they promised.
Exposing the PR Lies from HUB Management:
HUB recently updated their public response to my Google Review, claiming a "26-day delay" in property possession caused their bottleneck.
This is a blatant lie and complete mathematical fraud. According to their own official system-generated production calendar, the site installation kickoff was always scheduled for May 19th. Handing over the keys on May 21st is a mere 2-day operational variance, not 26 days. They are counting the internal factory time they required as a client delay! Furthermore, they claimed I paid milestone payments "without intimation"—an absolute logistics impossibility since their corporate accounts only accept milestone funds when system-triggered by their own production managers